Trying to seal some steel formwork from the inside, that has has an upper edge above water level that is to be pumped dry for the concrete pour, we have some tidal movement ~0.5m and 1kt of current in a river. Tried Leakmaster to no success and some luck with lead wool and vanex (super fast setting cement) gap size varies from .5mm to 20mm around pylons. water temp 14C
Any Ideas???
Previous pier we had to pour under water then hydro blast it level for the steelworkers to install the reo. Want to streamline the next pours.